by datafoundry | May 23, 2011 | Data Centers
The exterior of Texas 1 is almost complete! The parking lot has been paved, trees have been planted, and the exterior perimeter fence is going up. You can really start to see the scale of the building! Take a look around the property for yourself… May 2011 – The...
by datafoundry | May 11, 2011 | Data Centers
Texas 1 will serve as an office for a number of Data Foundry employees, as well as a temporary office for worksite recovery customers. Some of the details that make Texas 1 a welcoming environment are already going into place! Take a look… The entryway to Texas 1 is...
by datafoundry | May 6, 2011 | Data Centers
With Texas 1 opening in just a few weeks, we are excited to report that the power systems and controls supporting the facility have been fully installed! Texas 1 has fully redundant power from two separate substations. Our dual-feed power is carried all the way to the...
by datafoundry | May 5, 2011 | Press Releases
Austin, TX – MAY 5, 2011 – Data Foundry, a leading provider of wholesale and retail data center outsourcing, colocation, and disaster recovery services, announces it will host a job fair in Austin, Texas to fill open positions at its new master-planned data...