Construction of Houston 2 is moving forward extremely well! Over the past couple of weeks, crews made significant progress as the structural steel has been put in place, additional conduit has been positioned and the site cast concrete walls are set to be put in place at Houston 2. Construction of the structural steel is a major milestone because it acts as the “skeletal system” of the data center. It’s now getting easier to visualize exactly how massive this premium data center will be.
Panoramic Photos
Structural Steel Frame
Tilt Wall Casting Forms
Despite torrential rainfall in the Houston area, construction continues to hit deadlines and we march toward our next milestone, which will be the site cast concrete walls going up. Stay tuned for our next Houston 2 construction update in a couple of weeks!