The Generator Rooms

Construction has begun on the Generator Rooms. These rooms will house the generators to ensure there is always a redundant power supply within Texas 1 to support the heating, cooling and electrical hubs. This is the future home to six generators, which will provide over 12-megawatts of power.

2010 11 11 011
The grade beams, precast columns and double-T roof structure are in place. The thick, concrete masonry walls will be built on top of the grade-beams for added protection.
2010 11 11 165
The electrical conduits have been laid in the Mechanical/Chilled Water plant area.
2010 11 11 177
A view of the exhaust breezeway and precast panels being put into place. The crane is sitting where UPS Rooms 3 and 4 will essentially be.
2010 11 11 032
The generator walls have gone up!
2011 01 06 001 2011 01 06 001
An individual generator room.
3 23 11 203